Authors:
László Pusztai Department of Engineering Management, Faculty of Engineering, University of Debrecen, Ótemető u 2-4, H-4029 Debrecen, Hungary

Search for other papers by László Pusztai in
Current site
Google Scholar
PubMed
Close
,
Balázs Kocsi Department of Engineering Management, Faculty of Engineering, University of Debrecen, Ótemető u 2-4, H-4029 Debrecen, Hungary

Search for other papers by Balázs Kocsi in
Current site
Google Scholar
PubMed
Close
,
István Budai Department of Engineering Management, Faculty of Engineering, University of Debrecen, Ótemető u 2-4, H-4029 Debrecen, Hungary

Search for other papers by István Budai in
Current site
Google Scholar
PubMed
Close
, and
Lajos Nagy Institute of Sectoral Economics and Methodology, Faculty of Business and Economics, University of Debrecen, Böszörményi u. 138, H-4032 Debrecen, Hungary

Search for other papers by Lajos Nagy in
Current site
Google Scholar
PubMed
Close
Open access

Abstract:

A key role of production managers at manufacturing companies is to make economy-based decisions related to production scheduling. If the production is subject to uncertain factors, like human resource or lack of standardization, production planning becomes difficult and calls for advanced models that are tailored to the manufacturing process. This research investigates a real furniture manufacturing system from both managerial and materialflow points of view. Statistical simulation was run on the manufacturing process, where the possible production structures were given. ANOVA analysis was calculated in order to identify those activities that have the most significant influence on the profit.

Abstract:

A key role of production managers at manufacturing companies is to make economy-based decisions related to production scheduling. If the production is subject to uncertain factors, like human resource or lack of standardization, production planning becomes difficult and calls for advanced models that are tailored to the manufacturing process. This research investigates a real furniture manufacturing system from both managerial and materialflow points of view. Statistical simulation was run on the manufacturing process, where the possible production structures were given. ANOVA analysis was calculated in order to identify those activities that have the most significant influence on the profit.

1 Introduction

One of the greatest challenges that a manufacturing company may face is the material flow optimization. If the material flow is not balanced within a manufacturing process, it is possible that high work-in-process will be accumulated in the production, which always results in extra costs [1]. A major task under these circumstances is to determine an optimal or near the optimal production schedule that takes logistics 5R into account.

Another challenging problem is the stochastic behavior of activity durations. Due to the explosion of uncertain and stochastic factors, both the prediction of total lead time as well as making decisions on accepting or rejecting orders can be difficult. Taking these factors into consideration, a stochastic multi period production planning system should be applied [2].

2 Literature review

2.1 Operations research models for scheduling

Every company aims to satisfy their customer orders [3]. It can only be feasible if all the necessary raw materials and components are available in harmony with the 5Rs of the logistics. If one of these requirements is not adequate, extra costs should be paid [2].

Another important issue in the capability and the capacity of the manufacturing process: the decision about accepting or rejecting purchases depends on these indicators [3]. In the case of this kind of decision making problem, the objectives are the time and cost, in which balance should be found [4].

An effective way of production representation is the application of network models [5]. The representation of a network usually occurs with the use of a G(N,A) graph, where N displays nodes and A represents connections between the nodes. Nodes can symbolize anything: the meanings of these elements depend on the problems themselves and on analysts [6].

As far as production scheduling is concerned, there are numerous existing models: when it is a project under process, critical path method and process network methods can be used [7], [8], or Wagner-method is suitable for multi-period production planning [5]. Other cases, for example the material flow optimization, a generalized network flow model can be applied [9], and the list could be expanded.

Furthermore, the use of deterministic optimization cannot be the best choice, because in an always changing environment input values are not fixed. A good solution for this problem is the integration of operations research method with Monte-Carlo simulation technique [10]. In the recent years, several articles were published related to the combination of optimization and simulation, for instance [11], [12]. Investigating a system with the use of this method, can result in getting more reliable information which make decisions more grounded [12].

3 Methodology

3.1 Process presentation

The examined company deals with furniture manufacturing-to-order. Their major products are corpus and kitchen furniture. In this process, the use of corpus is optional: it can be either sold individually, or it can be built into the ready-made kitchen furniture. Corpus manufacturing consists of two activities: the preparation and the assembly phases. The kitchen furniture manufacturing involves several two phases: different sawing and wood planning activities, plus screwing, gluing, hinging activities. The full process map can be seen in Fig. 1. Purchase orders are based on the combination of these products. In order to analyze how much the profit is achievable in each of the product combinations, it is important to determine what kinds of order combinations can be feasible in this process environment.

Fig. 1.
Fig. 1.

Graph representation of the process

Citation: Pollack Periodica 15, 2; 10.1556/606.2020.15.2.5

3.2 Uncertain elements in the production

There are two elements in the manufacturing system those are considered uncertain: the activity times and the order combination. As far as the former indicator is concerned, 25 measurements were executed, and based on the measured data; a probability distribution was assigned to each activity - in this case, the theoretical distributions were applied to the activity on the basis of 11 measurements. The result can be seen in Table I.

Table I.

Uncertain activity times

Activity (xi)Minimum durationMaximum durationManufacturing costDistribution
x160 TMUs120 TMUs690 P$β [3;5]
x260 TMUs204 TMUs300 P$β [3;5]
x330 TMUs60 TMUs300 P$β [3;5]
x412 TMUs60 TMUs300 P$β [3;5]
x513.2 TMUs66 TMUs300 P$β [3;5]
x66 TMUs21 TMUs300 P$β [3;5]
x720.4 TMUs60 TMUs300 P$β [3;5]
x812 TMUs30 TMUs300 P$β [3;5]
x98.4 TMUs21.6 TMUs300 P$β [3;5]
x1060 TMUs228 TMUs300 P$β [3;5]

where xi is the activity ID; Minimum/maximum durations: the minimal and maximal cycle time of a certain activity (time duration values are indicated with Time Measurement Unit (TMU)); Manufacturing cost includes all the labor cost related to a carry out a certain activity (excluding the cost of the raw material); Distributions: the values in the brackets determine the shape of the distribution value (α,β values).

3.3 Proposed model

The proposed model is a stochastic multi-period production scheduling model with integer constraints.

Objective:

Just like at every manufacturing company, the examined objective is the maximization of the profit:
z=ProfitMAX!

Constraints:

  1. 1)Time constraints: Every order is considered as a project. An order has to be completed within 1 week, which equals 40 hours (2400 sec) based on the work schedule of the company. Therefore, the following equation can be drawn:
i=0nj=1mti,j24000min,
where i means the product type and j is the process step.
  1. 2)Demand constraints: There are two products in this project. These products are usually ordered in combinations. The following equations show the possible intervals of the ordered products:
x1,x1={0,1,2,3},
x2,x2={3,4,5,6}.
Furthermore, based on the product features, sold quantities have to be integer. In addition, the following equations were applied:
NumberofproducedproductgivendemandforproductA,
NumberofproducedproductgivendemandforproductB.
  1. 3)Raw materials: Due to the limited space of the warehouse, some resources are considered constraints in this case. Only those types of raw materials are listed here that have their effect on the possible solution set:
0UseWood15,
0UseWood27,
where Wood1 and Wood2 are different raw materials for kitchen furniture manufacturing. Nevertheless, all of the raw material was built into the model in order to see the consumptions of them.

Decision variables:

In this case study, the decision variables represent the material flow. They indicate how much raw or semi processed material travels from one activity to another: these are called Work-In-Process (WIP). WIP shows all the connection between process activities, that is why it is a key factor in a production system.

In addition, it displays how many products are sold in a given week. Based on the model, the goal was to maximize the profit, which was the objective of the built-up network model.

4 Results

4.1 Results of the simulation

A deterministic model was constructed on the basis of the previously presented data (1)-(8). Furthermore, MS Excel’s Solver add-in was used for optimization. After creating the deterministic model, the environment for that of the stochastic was also elaborated. The simulation was programmed in Visual Basic Application programming language. The simulation was run 10,000 times, and the results were exported to an analyzable database. The descriptive statistics of the simulation can be seen in Table II.

Table II.

Results of the simulation - Descriptive statistics of time durations

NMedianStd. DeviationRangeMinimumMaximum
Duration-x110000829.5285461115
Duration-x21000011323.24812963192
Duration-x310000414.804263157
Duration-x410000307.759431356
Duration-x510000338.550501464
Duration-x610000122.46214721
Duration-x710000356.419352257
Duration-x810000192.895161329
Duration-x910000142.16812921
Duration-x101000012227.29714963212

Focusing on the order combinations, the following data were simulated. The first figure of the product combination is used for the number of corpus, while the second figure means the number of the kitchen furniture. It can be seen in Table III.

Table III.

Results of the simulation - Product combinations and their frequencies

Product combination1_40_52_40_41_52_32_53_41_30_6
Frequency36362069204515524801115029208
Percentage (%)36.4%20.7%20.5%15.5%4.8%1.1%0.5%0.3%0.2%0.1%
Cumulative percentage(%)36.4%57.1%77.5%93.0%97.8%98.9%99.499.7%99.9%100.0%

These production combinations represent most of the possible orders. The orders of extreme amounts were excluded from the simulation, because they must be dealt with individually. These orders usually request for high amounts, however, their frequency is quite low. The results of the simulation on purchasing orders reflect real data.

The most demanded product combinations are:

  • 1 corpus + 4 furniture pieces (hereinafter 1_4);

  • 2 corpuses + 4 furniture pieces(hereinafter 2_5);

  • 4 kitchen furniture pieces (hereinafter 0_4);

  • 5 kitchen furniture pieces (hereinafter 0_5).

4.2 Indicators under investigation

Work-time utilization

Work-time utilization is a very important part of the production: it sheds light on time puffers and helps to handle unplanned obstacles in the production, for instance delivery delays or machine repairs. Work-time utilization can be calculated with the following equation:
Utilization=TotalprocesstimeAvailabletimeforproductioninacertainweek

Furthermore, the efficiency of the production can be analyzed by this calculation. An important standpoint is to find the balance value between utilization and work-time.

As far as the production is concerned, Analysis Of Variance (ANOVA) analysis was carried out after the completion of normality test in order to see if there are any differences between product combinations in respect of work utilization. The grouping variable was the production structure, while the measured indicator was the utilization.

The ANOVA test was significant (p0.05;n=10,000)

The ANOVA test was significant (p0.05),and the completion of Tukey-b post-hoc test proved that the work utilizations of the order combinations are statistically different (Table IV).

Table IV.

Results of Tukey-b Post-hoc analysis

Order combinationsNTime utilization
Subset for alpha = 0.05
1234
0_4155294.15%
1_4363695.64%
0_5206997.03%97.03%
2_4204597.67%

Profit calculation

Profit is the subtraction of the income and costs:
Unitprofit=unitpriceunitcost.

Small and medium sized enterprises employing human workforce can only make rough estimations about their profit due to the unpredictability of total process times in the production. Furthermore, additional machine set-ups or repairs may arise that can extend the duration of activities. This stochastic background does not guarantee the even nature of profit generation. Based on the values gained by the simulation, more valid estimations can be calculated about purchase orders.

It is a very informative part of the research, because by being aware of the most profitable order combinations, companies can control and affect their customers’ needs. The descriptive statistics on profits generated by the most frequently ordered product combinations is displayed in Fig. 2 and Table V.

Fig. 2.
Fig. 2.

Probable profits by order combinations

Citation: Pollack Periodica 15, 2; 10.1556/606.2020.15.2.5

Table V.

Descriptive statistics about the probable profit by order combinations

0_40_51_42_4
Mean (TMU)331 623416 087350 905370 276
Median (TMU)331 618416 105350 924370 291
Std. Deviation (TMU)530590585613
Minimum (TMU)330 022414 333348 738368 282
Maximum (TMU)333 176418 018352 515372 413

As it can be seen in Fig. 2 and Table V, the range of probable profits is around 4,000 in the case of each order combinations. It helps the company to make plans for the future. In the model the cost of raw material and that of employment are indicated separately. The model does not include the occurrence of defected products; therefore, the estimated cost of human workforce is presented in the following chart, see Fig. 3.

Fig. 3.
Fig. 3.

Probable cost of human workforce by order combinations

Citation: Pollack Periodica 15, 2; 10.1556/606.2020.15.2.5

The cost of raw material is directly proportional with the produced quantity; the occurrence of the defects and their effects are not modeled.

Correlations between profit and activity time durations

As it was mentioned in the previous section more human work results in higher costs. With the use of correlation analysis, relationships are revealed between profit and activities, that is, which activities have the strongest influence on the profit. It can also highlight activities that must be improved first. The result of the analysis can be seen in the Table VI.

Table VI.

Results of the simulation - Product combinations and their frequencies

ProfitDuration x3Duration x4Duration x5Duration x6Duration x7Duration x8Duration x9Duration x1Duration x2Duration x10
Profit1-.115-.163-.189-.056-.137-.060-.029-.260-.593-.576
Duration x3100.002.01-.005.005-.01.004.012
Duration x410.006.003.008.013-.013.001-.012
Duration x51-.012-.001-.029-.019.007.004-.004
Duration x61-.005-.004.007.0080.003
Duration x71-.008-.007.009-.01-.003
Duration x81.004-.016.006.003
Duration x91.002-.025-.011
Duration x11.013-.001
Duration x21.002
Duration x101

Results of the simulation - Product combinations and their frequencies

The result of the analysis is evident: negative correlation can be identified between the activity times (plus the costs) and the profit. Based on the results in the table above, there are strong negative correlations between the profit and (Duration-x2; Duration-x10) activities, while the other activities show weaker or zero correlations with the profit. In other words, the improvement of activities (Activity2; Activity10) can generate higher profit values, as well as it may lead to either lower costs, or the production of extra pieces (it also means extra profit for the company).

5 Conclusion

The aim of each company is to earn profit, while they are trying to optimize the utilization of all their resources. In this case study, stochastic operations of a manufacturing system were modeled through a stochastic multi-period production scheduling model. Based on the gathered and measured data from a real life furniture manufacturing system, indicators like raw material usage, probable working hours, work utilization, expected profit and costs can be calculated. With the application of this analysis, the most profitable product combinations were determined and the most crucial activities were revealed to see where the process improvement should be applied.

Acknowledgement

This work was supported by the construction EFOP-3.6.3-VEKOP-16. The project was supported by the European Union, co-financed by the European Social Fund.

References

  • [1]

    Womack J. P., Jones D. T. Lean thinking, Banish waste and create wealth in your corporation, revised and updated, Simon & Schuster, New York, 1996.

    • Search Google Scholar
    • Export Citation
  • [2]

    Winston W. L. Operations research: Applications and algorithms, Duxbury Press, Boston, 2004.

  • [3]

    Heizer J. H., Render B. Principles of operations management, Prentice-Hall, 1997.

  • [4]

    Csordas H. Activities with multi-parameters in time-cost trade-off, Pollack Periodica , Vol. 6, No. 2, 2011, pp. 3748.

  • [5]

    Temesi J., Varró Z. Operations research (in Hungarian), Akadémiai Kiadó, Budapest, 2014.

  • [6]

    Ragsdale C. Spreadsheet modeling & decision analysis, A practical introduction to management science (with essential resources printed access card), Nelson Education Ltd, 2017.

    • Search Google Scholar
    • Export Citation
  • [7]

    Ercsey Zs. Process network solution of a clothing manufacturer’s problem, Pollack Periodica, Vol. 12, No. 1, 2017, pp. 5967.

  • [8]

    Vincze N., Ercsey Zs., Kovacs T., Tick J., Kovacs Z. Process network solution of extended CPM problems with alternatives, Acta Polytechnica Hungarica, Vol. 13, No. 3, 2016, pp. 101117.

    • Search Google Scholar
    • Export Citation
  • [9]

    Pusztai L. P., Kocsi B., Budai I., Nagy L. Material flow optimization with the application of generalized network flow, (in Hungarian) Műszaki Tudományos Közlemények , Vol. 9, 2018, pp. 203206.

    • Search Google Scholar
    • Export Citation
  • [10]

    Stevenson W. Operations management, McGraw Hill, 2014.

  • [11]

    Mourtzis D., Doukas M. Bernidaki D. Simulation in manufacturing: review and challenges, Procedia CIRP, Vol. 25, 2014, pp. 213229.

  • [12]

    Kikolski M. Study of production scenarios with the use of simulation models, Procedia Engineering, Vol. 182, 2017, pp. 321328.

  • [1]

    Womack J. P., Jones D. T. Lean thinking, Banish waste and create wealth in your corporation, revised and updated, Simon & Schuster, New York, 1996.

    • Search Google Scholar
    • Export Citation
  • [2]

    Winston W. L. Operations research: Applications and algorithms, Duxbury Press, Boston, 2004.

  • [3]

    Heizer J. H., Render B. Principles of operations management, Prentice-Hall, 1997.

  • [4]

    Csordas H. Activities with multi-parameters in time-cost trade-off, Pollack Periodica , Vol. 6, No. 2, 2011, pp. 3748.

  • [5]

    Temesi J., Varró Z. Operations research (in Hungarian), Akadémiai Kiadó, Budapest, 2014.

  • [6]

    Ragsdale C. Spreadsheet modeling & decision analysis, A practical introduction to management science (with essential resources printed access card), Nelson Education Ltd, 2017.

    • Search Google Scholar
    • Export Citation
  • [7]

    Ercsey Zs. Process network solution of a clothing manufacturer’s problem, Pollack Periodica, Vol. 12, No. 1, 2017, pp. 5967.

  • [8]

    Vincze N., Ercsey Zs., Kovacs T., Tick J., Kovacs Z. Process network solution of extended CPM problems with alternatives, Acta Polytechnica Hungarica, Vol. 13, No. 3, 2016, pp. 101117.

    • Search Google Scholar
    • Export Citation
  • [9]

    Pusztai L. P., Kocsi B., Budai I., Nagy L. Material flow optimization with the application of generalized network flow, (in Hungarian) Műszaki Tudományos Közlemények , Vol. 9, 2018, pp. 203206.

    • Search Google Scholar
    • Export Citation
  • [10]

    Stevenson W. Operations management, McGraw Hill, 2014.

  • [11]

    Mourtzis D., Doukas M. Bernidaki D. Simulation in manufacturing: review and challenges, Procedia CIRP, Vol. 25, 2014, pp. 213229.

  • [12]

    Kikolski M. Study of production scenarios with the use of simulation models, Procedia Engineering, Vol. 182, 2017, pp. 321328.

  • Collapse
  • Expand

Senior editors

Editor(s)-in-Chief: Iványi, Amália

Editor(s)-in-Chief: Iványi, Péter

 

Scientific Secretary

Miklós M. Iványi

Editorial Board

  • Bálint Bachmann (Institute of Architecture, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Jeno Balogh (Department of Civil Engineering Technology, Metropolitan State University of Denver, Denver, Colorado, USA)
  • Radu Bancila (Department of Geotechnical Engineering and Terrestrial Communications Ways, Faculty of Civil Engineering and Architecture, “Politehnica” University Timisoara, Romania)
  • Charalambos C. Baniotopolous (Department of Civil Engineering, Chair of Sustainable Energy Systems, Director of Resilience Centre, School of Engineering, University of Birmingham, U.K.)
  • Oszkar Biro (Graz University of Technology, Institute of Fundamentals and Theory in Electrical Engineering, Austria)
  • Ágnes Borsos (Institute of Architecture, Department of Interior, Applied and Creative Design, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Matteo Bruggi (Dipartimento di Ingegneria Civile e Ambientale, Politecnico di Milano, Italy)
  • Petra Bujňáková (Department of Structures and Bridges, Faculty of Civil Engineering, University of Žilina, Slovakia)
  • Anikó Borbála Csébfalvi (Department of Civil Engineering, Institute of Smart Technology and Engineering, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Mirjana S. Devetaković (Faculty of Architecture, University of Belgrade, Serbia)
  • Szabolcs Fischer (Department of Transport Infrastructure and Water Resources Engineering, Faculty of Architerture, Civil Engineering and Transport Sciences Széchenyi István University, Győr, Hungary)
  • Radomir Folic (Department of Civil Engineering, Faculty of Technical Sciences, University of Novi Sad Serbia)
  • Jana Frankovská (Department of Geotechnics, Faculty of Civil Engineering, Slovak University of Technology in Bratislava, Slovakia)
  • János Gyergyák (Department of Architecture and Urban Planning, Institute of Architecture, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Kay Hameyer (Chair in Electromagnetic Energy Conversion, Institute of Electrical Machines, Faculty of Electrical Engineering and Information Technology, RWTH Aachen University, Germany)
  • Elena Helerea (Dept. of Electrical Engineering and Applied Physics, Faculty of Electrical Engineering and Computer Science, Transilvania University of Brasov, Romania)
  • Ákos Hutter (Department of Architecture and Urban Planning, Institute of Architecture, Faculty of Engineering and Information Technolgy, University of Pécs, Hungary)
  • Károly Jármai (Institute of Energy and Chemical Machinery, Faculty of Mechanical Engineering and Informatics, University of Miskolc, Hungary)
  • Teuta Jashari-Kajtazi (Department of Architecture, Faculty of Civil Engineering and Architecture, University of Prishtina, Kosovo)
  • Róbert Kersner (Department of Technical Informatics, Institute of Information and Electrical Technology, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Rita Kiss  (Biomechanical Cooperation Center, Faculty of Mechanical Engineering, Budapest University of Technology and Economics, Budapest, Hungary)
  • István Kistelegdi  (Department of Building Structures and Energy Design, Institute of Architecture, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Stanislav Kmeť (President of University Science Park TECHNICOM, Technical University of Kosice, Slovakia)
  • Imre Kocsis  (Department of Basic Engineering Research, Faculty of Engineering, University of Debrecen, Hungary)
  • László T. Kóczy (Department of Information Sciences, Faculty of Mechanical Engineering, Informatics and Electrical Engineering, University of Győr, Hungary)
  • Dražan Kozak (Faculty of Mechanical Engineering, Josip Juraj Strossmayer University of Osijek, Croatia)
  • György L. Kovács (Department of Technical Informatics, Institute of Information and Electrical Technology, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Balázs Géza Kövesdi (Department of Structural Engineering, Faculty of Civil Engineering, Budapest University of Engineering and Economics, Budapest, Hungary)
  • Tomáš Krejčí (Department of Mechanics, Faculty of Civil Engineering, Czech Technical University in Prague, Czech Republic)
  • Jaroslav Kruis (Department of Mechanics, Faculty of Civil Engineering, Czech Technical University in Prague, Czech Republic)
  • Miklós Kuczmann (Department of Automations, Faculty of Mechanical Engineering, Informatics and Electrical Engineering, Széchenyi István University, Győr, Hungary)
  • Tibor Kukai (Department of Engineering Studies, Institute of Smart Technology and Engineering, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Maria Jesus Lamela-Rey (Departamento de Construcción e Ingeniería de Fabricación, University of Oviedo, Spain)
  • János Lógó  (Department of Structural Mechanics, Faculty of Civil Engineering, Budapest University of Technology and Economics, Hungary)
  • Carmen Mihaela Lungoci (Faculty of Electrical Engineering and Computer Science, Universitatea Transilvania Brasov, Romania)
  • Frédéric Magoulés (Department of Mathematics and Informatics for Complex Systems, Centrale Supélec, Université Paris Saclay, France)
  • Gabriella Medvegy (Department of Interior, Applied and Creative Design, Institute of Architecture, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Tamás Molnár (Department of Visual Studies, Institute of Architecture, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Ferenc Orbán (Department of Mechanical Engineering, Institute of Smart Technology and Engineering, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Zoltán Orbán (Department of Civil Engineering, Institute of Smart Technology and Engineering, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Dmitrii Rachinskii (Department of Mathematical Sciences, The University of Texas at Dallas, Texas, USA)
  • Chro Radha (Chro Ali Hamaradha) (Sulaimani Polytechnic University, Technical College of Engineering, Department of City Planning, Kurdistan Region, Iraq)
  • Maurizio Repetto (Department of Energy “Galileo Ferraris”, Politecnico di Torino, Italy)
  • Zoltán Sári (Department of Technical Informatics, Institute of Information and Electrical Technology, Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Grzegorz Sierpiński (Department of Transport Systems and Traffic Engineering, Faculty of Transport, Silesian University of Technology, Katowice, Poland)
  • Zoltán Siménfalvi (Institute of Energy and Chemical Machinery, Faculty of Mechanical Engineering and Informatics, University of Miskolc, Hungary)
  • Andrej Šoltész (Department of Hydrology, Faculty of Civil Engineering, Slovak University of Technology in Bratislava, Slovakia)
  • Zsolt Szabó (Faculty of Information Technology and Bionics, Pázmány Péter Catholic University, Hungary)
  • Mykola Sysyn (Chair of Planning and Design of Railway Infrastructure, Institute of Railway Systems and Public Transport, Technical University of Dresden, Germany)
  • András Timár (Faculty of Engineering and Information Technology, University of Pécs, Hungary)
  • Barry H. V. Topping (Heriot-Watt University, UK, Faculty of Engineering and Information Technology, University of Pécs, Hungary)

POLLACK PERIODICA
Pollack Mihály Faculty of Engineering
Institute: University of Pécs
Address: Boszorkány utca 2. H–7624 Pécs, Hungary
Phone/Fax: (36 72) 503 650

E-mail: peter.ivanyi@mik.pte.hu 

or amalia.ivanyi@mik.pte.hu

Indexing and Abstracting Services:

  • SCOPUS
  • CABELLS Journalytics

 

2023  
Scopus  
CiteScore 1.5
CiteScore rank Q3 (Civil and Structural Engineering)
SNIP 0.849
Scimago  
SJR index 0.288
SJR Q rank Q3

Pollack Periodica
Publication Model Hybrid
Submission Fee none
Article Processing Charge 900 EUR/article
Printed Color Illustrations 40 EUR (or 10 000 HUF) + VAT / piece
Regional discounts on country of the funding agency World Bank Lower-middle-income economies: 50%
World Bank Low-income economies: 100%
Further Discounts Editorial Board / Advisory Board members: 50%
Corresponding authors, affiliated to an EISZ member institution subscribing to the journal package of Akadémiai Kiadó: 100%
Subscription fee 2025 Online subsscription: 381 EUR / 420 USD
Print + online subscription: 456 EUR / 520 USD
Subscription Information Online subscribers are entitled access to all back issues published by Akadémiai Kiadó for each title for the duration of the subscription, as well as Online First content for the subscribed content.
Purchase per Title Individual articles are sold on the displayed price.

 

2023  
Scopus  
CiteScore 1.5
CiteScore rank Q3 (Civil and Structural Engineering)
SNIP 0.849
Scimago  
SJR index 0.288
SJR Q rank Q3

Monthly Content Usage

Abstract Views Full Text Views PDF Downloads
Apr 2024 0 47 15
May 2024 0 40 11
Jun 2024 0 87 3
Jul 2024 0 38 13
Aug 2024 0 59 6
Sep 2024 0 58 4
Oct 2024 0 30 1